Print Friendly VersionPROJECT SCHEDULEThis page is intended to provide a an overview of the events that will occur in the next 2-3 months. Where possible, specific dates are provided. In other cases, general timeframes are given. The information and dates are subject to change as necessary to accommodate the progress of the Part 150 Study. So, please check back periodically for the latest information regarding the study.
September 2004Planning Advisory Committee Meeting #3 - September 1, 2004
Master Plan
Part 150 Preparation of New 2010 Baseline Noise Contour (growth without DHL)
October 2004Master Plan Completion and Approval of Aviation Forecasts
Part 150 Modeling and Documenting Noise Abatement Alternatives Development and Evaluation of Land Use Alternatives
November 2004 Planning Advisory Committee Meeting #4 - November 17, 2004
Master Plan
Part 150 Presentation of Preliminary Noise Abatement Recommendations Presentation of Preliminary Land Use Recommendations December 2004Master Plan Master Plan Alternatives Refinement
Part 150 Refinement of Recommended Noise Abatement Alternatives Refinement of Recommended Land Use Alternatives Development of Preliminary Noise Compatibility Program